WHAT should have been a winter works job is now being started in August.
Work on Millwall Cutting Bridge will close the navigation to Millwall Inner Dock for 10 weeks tells the stoppage notice, Keith Gudgin reports.
Confusing
Yet the notice also states the navigation closure starts Monday 2st1 August until Monday 16th October—eight weeks, that will be confusing to those mooring there.
The works will be to remove and replace both electrical and hydraulic components of the bridge operating systems.
As this means the bridge will have no power it cannot be operated and will remain in the down position so no boats will be able to pass through.